Client
Portakabin Total Solutions
Date
Contract Awarded November 2016. Completed in February 2017.
Portakabin engaged with the Remark Group to design and undertake the installation of electrical supplies to a new school currently being constructed next to London City Airport.
Remark strategically planned this complex project to deliver all aspects of the work for Portakabin to supply section of the school. Our dedicated Project Manager established and maintained communication links between all parties to ensure project was delivered on time and within budget.
The work included UK Power Network installing an 11KV transformer substation on the site and Remark supplying the 500 amps 3 phase supply from this to the main distribution panel and then installing submains to each of the distribution board.
To ensure the site infrastructure was suitable for future use, Remark worked closely with the design team to ensure there was sufficient capacity for phase 2. We liaised with Portakabin to achieve a non-obtrusive cable route for multiple sub main cables. Remark UKPN had to install an extend the High voltage ring into the site and install a new transformer to supply the site.
During the project there were a number of changes to the original loading requirements to the building. Remark were able to react responsively and obtained key materials within 24hours to keep the project progressing.
There were also many Health & Safety restraints to work around. We assessed the risks with the onsite management teams to ensure suitable RAMS were in place and works were undertaken in a correct and safe manner, putting the safety of the working individual’s foremost.
Commercial Electrical & Network Infrastructure for VentfiltersRus’ New Warehouse
Sep 4, 2026
Improving Speech Privacy at Community Network Services
Jul 30, 2026
Quai Digital Office Technology Case Study
AV
—
Nov 11, 2025
Cost of poor Wi-Fi for businesses & what you can do about it
Nov 1, 2025
Improve your large meeting space to create impact
To improve the sound quality in new or existing auditoriums, contact our audio experts today.